03/2018: Monthly update for January 2018


  • In January 2018, the total wind production was 14% above estimates.
  • On the one hand, due to favourable wind conditions, the Italian wind farms performed significantly above budget: 27%. On the other hand, the Spanish and Polish wind turbines performed lower than expected but fairly higher (+9%) than the same period last year.



  • In January 2018, the total solar production was 8% higher than estimated.
  • The average irradiation was fairly higher than expected in Italy and slightly lower than expected in Spain which was compensated by a good availability of the La Castilleja plant. The Italian and Spanish solar plants delivered a production of +10% and +4% respectively compared to estimates.